energy · the national build-out

Britain’s clean power build-out

Every renewable and low-carbon power project in Britain's planning database, from the Renewable Energy Planning Database. This is the build-out: what is operating, what has consent and is waiting to be built, and what is still in planning, by technology, company and nation. 58.6 GW is operational, with far more in the pipeline.

How to read this

The Renewable Energy Planning Database tracks projects above 150 kW through planning, from application to operation. It is a record of the pipeline, not a measure of electricity generated. Capacity is installed megawatts, not the power actually produced, which depends on the wind and the sun.

Every figure is computed from the published database, the Q2 2026 extract with records updated to July 2026. Project locations come from the grid reference on each record.

58.6
GW operating
147
GW awaiting construction
14,657
projects tracked

The pipeline

Built, being built, and waiting

58.6 GW of clean power is operating today. Another 147.0 GW already has planning consent but has not been built, the single biggest block in the pipeline, which points at grid connection and finance rather than planning as the hold-up.

Operationaloperating now
58.6 GW3,132 projects
Under Constructionbeing built
28.1 GW457 projects
Awaiting Constructionconsent granted, not yet built
147 GW5,948 projects
Application Submittedin planning
95.1 GW1,539 projects
Application Refusedrefused
19.3 GW941 projects

The mix

What is generating now

Operational capacity by technology. It is a broad mix: onshore and offshore wind and solar lead, but battery storage, biomass, pumped storage and hydro all feature.

Wind Offshore
16 GW49
Wind Onshore
15.5 GW785
Solar Photovoltaics
11.1 GW1,407
Battery
5 GW178
Biomass (dedicated)
3.5 GW81
Pumped Storage Hydroelectricity
2.8 GW4
EfW Incineration
1.5 GW61
Landfill Gas
0.8 GW270
Biomass (co-firing)
0.7 GW2

Across the nations

Where the operating capacity sits

Operational capacity by nation. England has the most in total; Scotland carries a large share for its size, with onshore wind to the fore.

England
34.5 GW2,170 projects
Scotland
17.3 GW593 projects
Wales
5.3 GW248 projects
Northern Ireland
1.5 GW119 projects

Year by year

How fast it has been built

New operational capacity added each year. The pace has been uneven, and the recent years sit below the middle of the last decade even as the consented backlog has grown.

GW of new operational capacity added each year. 2026 is a partial year. Source: Renewable Energy Planning Database.

Who builds it

The biggest operators

The companies with the most operational capacity. A handful of large developers, several of them offshore wind specialists, account for a big share.

1.Orsted (formerly Dong Energy)
4.4 GW13 sites
2.Drax Power
2.6 GW4 sites
3.First Hydro Company
2.1 GW2 sites
4.Scottish Power Renewables
2 GW22 sites
5.Scottish and Southern Energy (SSE)
1.7 GW55 sites
6.Vattenfall
1.1 GW11 sites
7.SSE / Seagreen Wind Energy Ltd
1.1 GW1 sites
8.Diamond Green Limited, CTG & Ocean Winds
0.9 GW1 sites

Close to home

The build-out in West Lothian

West Lothian has 54 projects in the database, 0.9 GW in all, of which 0.1 GW is operating. The striking local trend is battery storage: 11 of the 54 are battery projects, alongside onshore wind such as Tormywheel and Longhill Burn. The county is becoming a place where power is stored as well as made.

54
projects
0.9
GW total
0.1
GW operating
11
battery projects
SiteTechnologyMWStatus
Pond Industrial Park, Whitburn Road - Pond Battery StorageBattery200Awaiting Construction
Drumshoreland Road Battery Storage FacilityBattery49.9Awaiting Construction
Middlerigg - Battery Energy StorageBattery49.9Awaiting Construction
Fauch HillWind Onshore48Appeal Refused
Longhill Burn Wind FarmWind Onshore45.6Under Construction
Gladsmuir Hills - Wind FarmWind Onshore41Awaiting Construction
Leyden Road - Solar ArraySolar Photovoltaics40Application Submitted
TormywheelWind Onshore30.8Operational
Drumcross Battery StorageBattery30Awaiting Construction
Learielaw FarmBattery29.9Revised

Questions this raises

For developers, the grid and government

  1. 1.

    147.0 GW has consent but is not built. Is the grid connection queue, not planning, now the real constraint on clean power?

  2. 2.

    Battery storage is the fastest-growing category, locally and nationally. Is the planning and grid system keeping pace with storage as well as generation?

  3. 3.

    New operational capacity in recent years sits below the middle of the last decade. What would it take to build the consented pipeline out faster?

  4. 4.

    A small number of large developers dominate. Is there room for more community and locally owned schemes?

Sources & method

Data provenance

Caveats & data notes

  • The database tracks projects above 150 kW through planning. It is a pipeline record, not a measure of electricity generated.
  • Capacity is installed megawatts. Actual output depends on the technology and the weather, so a megawatt of solar and a megawatt of gas are not the same in practice.
  • Status reflects the latest planning stage recorded. The pipeline shifts each quarter as projects progress, are refused or are abandoned.
  • West Lothian projects are identified by the county and planning authority fields.
  • Contains public sector information licensed under the Open Government Licence v3.0.